View Issue Details
| ID | Project | Category | View Status | Date Submitted | Last Update |
|---|---|---|---|---|---|
| 0002036 | T99X171.00 SKB Eagle | General | public | 2025-03-27 15:26 | 2025-07-04 16:58 |
| Reporter | (ALTech) SH Son | Assigned To | (MFG) Rachel Ruan | Due Date | |
| Priority | normal | Severity | s4-minor | Reproducibility | have not tried |
| Status | closed | Resolution | fixed | ||
| Summary | 0002036: [EAGLE] 2025.03 Mass production inspection Report | ||||
| Description | [EAGLE] 2025.03 Mass production inspection Report | ||||
| Tags | No tags attached. | ||||
| Attach Tags | |||||
| related to | 0001662 | new | [Eagle] Mass production inspection Report | |
| related to | 0002037 | closed | (PM) Roisy Liang | [Eagle] 2025.03 Monthly RMA_KR (Lot 24) shipping list |
| User List |
(ALTech) BY Lee , (ALTech) Hyunsik Kim , (ALTech) JW Kim , (ALTech) Lonnie Kim , (ALTech) SH Son , (ALTech) Sophie Lee , (ALTech) SY Yoon , (MFG) An Tran , (MFG) Rachel Ruan , (MFG) Toney Tu , (PM) Sheila Tu , (PM) Tiffanie Lai , |
|---|
|
|
Hi Rachel Here is inspection report of this month. • Minor HDMI cable function NG * 2pcs Please find the attachment file, and defect sample will be delivered with RMA retrun box I will update shipping information Thanks SON |
|
|
Dear Mr Son Thanks for the feedback! We will feedback " HDMI cable function NG * 2pcs on end user side " issue to the vendor to sorting in the vendor's goods stock , Preparing for the April/2025 70K production run. We would like to confirm that after sorting, where on the HDMI cable can we remark? Many Thanks Rachel |
|
|
Hi Rachel, First of all, this Cable NG is not on the end-user side. It was found during the customer's incoming inspection (IQC). I have also updated the cosmetic NG case. Please find the attached file. Additionally, I agree with sorting the HDMI cables. However, the customer does not want to remark directly on the HDMI cables. Therefore, I suggest instead marking point that the cable tie if you have any question, please contact me. Thanks SON |
|
|
Dear Mr Son Thanks so much. Ok, and we will update the vendor sorting result when they finish sorting. And when we receive the NG HDMI cable, we will analyze it. Many Thanks Rachel |
|
|
Hi Rachel. the defect HDMI cable will be ship together RMA box No. 2 https://btracker-cns.fii-foxconn.com/vaas/view.php?id=2037 Please refer to the attachment pitcher. Thanks SON |
|
|
Dear Mr Son OK Thanks so much. Rachel |
|
|
Hi Rachel Please analyze this defect cable and update the FA report schedule Thanks SON |
|
|
Dear MR Son The current RMA shipment is going through VN customs, according to PM's plan, it can only enter the factory in the middle of next week. When we receive HDMI NG, we will send it to the supplier for analysis. In addition, we also update the sorting results at Foxconn and FIT vendor. Pls check the file. Many thanks Rachel |
|
|
Dear Mr Son 05/29, We just received the HDMI cable from the RMA batch. We Re-tested the HDMI cable at the OBA station and confirmed that 2 pcs of HDMI are functionally defective, not connecting signal to TV and 01 pcs has an appearance defect. 05/30, we will deliver 3 pcs of HDMI to FIT vendor for more detailed analysis. Many thanks Rachel |
|
|
Hi Rachel Please update vendor analysis. Thanks SON |
|
|
Dear Mr Son We update FIT vendor FA report: HDMI cable cosmetic and Function issue: 1. Cause of the appearance defect: During the adhesive application process, the wires were not placed separately as required, and the outer molds were stacked crosswise, resulting in adhesive contamination on the outer mold. 2. Cause of the Function electrical defect leakage is that the employees did not strictly follow the 90-degree up-and-down shaking test. During the retesting of the defects, it was found that when the shaking amplitude was around 45-60 degrees, both the electrical test and the TV test were OK. However, when the shaking amplitude was around 90 degrees up and down, the defect of intermittent disconnection during shaking appeared, => Root cause for the appearance defect leakage is that the contamination of the outer mold with glue is relatively minor. The inspectors did not focus on this type of defect, resulting in the oversight during the inspection process. Action: 1. Conduct training for external inspectors and introduce a trap test assessment on the issue of foreign molds being glued to enhance employee alertness. 2.The improvement action, the shaking test angle reaches 90 degrees, and only then does the switch trigger to proceed to the next step. Additional shaking test has been added, with a 200% test to prevent any missed tests. Pls help review FIT FA report detail. Many thanks Rachel |
|
|
Hi Rachel. confirm the FIT vendor FA report Thank you for your support Thanks SON |
| Date Modified | Username | Field | Change |
|---|---|---|---|
| 2025-03-27 15:26 | (ALTech) SH Son | New Issue | |
| 2025-03-27 15:26 | (ALTech) SH Son | Relationship added | related to 0001662 |
| 2025-03-27 15:28 | (ALTech) SH Son | Note Added: 0017384 | |
| 2025-03-27 15:28 | (ALTech) SH Son | File Added: [EAGLE] 2025.03_Mass production inspection_rev01.pdf | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) BY Lee | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) Hyunsik Kim | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) JW Kim | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) Lonnie Kim | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) SH Son | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) Sophie Lee | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) Sun Choul Joung | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (ALTech) SY Yoon | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (MFG) An Tran | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (MFG) Rachel Ruan | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (MFG) Toney Tu | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (PM) Sheila Tu | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (PM) Tiffanie Lai | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue Monitored: (Sales) Miya Wang | |
| 2025-03-27 15:29 | (ALTech) SH Son | Issue End Monitor: (ALTech) Sun Choul Joung | |
| 2025-03-27 15:29 | (ALTech) SH Son | Assigned To | => (MFG) Rachel Ruan |
| 2025-03-27 15:29 | (ALTech) SH Son | Status | new => assigned |
| 2025-03-27 16:41 | (MFG) Rachel Ruan | Note Added: 0017387 | |
| 2025-03-27 16:41 | (MFG) Rachel Ruan | File Added: HDMI cable picture.jpeg | |
| 2025-03-28 09:48 | (ALTech) SH Son | Note Added: 0017388 | |
| 2025-03-28 09:48 | (ALTech) SH Son | File Added: image.png | |
| 2025-03-28 09:48 | (ALTech) SH Son | File Added: [EAGLE] 2025.03_Mass production inspection_rev02.pdf | |
| 2025-03-28 11:57 | (MFG) Rachel Ruan | Note Added: 0017389 | |
| 2025-04-03 09:44 | (ALTech) SH Son | Relationship added | related to 0002037 |
| 2025-04-03 09:49 | (ALTech) SH Son | Note Added: 0017394 | |
| 2025-04-03 09:49 | (ALTech) SH Son | File Added: image-2.png | |
| 2025-04-03 19:40 | (MFG) Rachel Ruan | Note Added: 0017398 | |
| 2025-04-07 09:24 | (SW) Willin Deng | Severity | s2-severe => s4-minor |
| 2025-05-21 13:48 | (ALTech) SH Son | Note Added: 0017554 | |
| 2025-05-21 14:55 | (MFG) Rachel Ruan | Note Added: 0017555 | |
| 2025-05-21 14:55 | (MFG) Rachel Ruan | File Added: HDMI Sorting result.xlsx | |
| 2025-05-21 14:55 | (MFG) Rachel Ruan | File Added: HDMI after sorting remark.png | |
| 2025-05-29 17:28 | (MFG) Rachel Ruan | Note Added: 0017570 | |
| 2025-06-17 10:52 | (ALTech) SH Son | Note Added: 0017595 | |
| 2025-06-17 17:18 | (MFG) Rachel Ruan | Note Added: 0017597 | |
| 2025-06-17 17:18 | (MFG) Rachel Ruan | File Added: 371.01057.005分析報告20250610A.pptx | |
| 2025-06-18 14:51 | (ALTech) SH Son | Note Added: 0017598 | |
| 2025-06-18 14:55 | (ALTech) SH Son | Status | assigned => confirmed |
| 2025-07-04 16:58 | (PM) Sheila Tu | Status | confirmed => closed |
| 2025-07-04 16:58 | (PM) Sheila Tu | Resolution | open => fixed |